All Case Studies
Food ProcessingPlant CommissioningMiddle East2024
High-Speed FMCG Packaging Line
Supply and commissioning of a 600 ppm primary + secondary + end-of-line packaging system with vision inspection and traceability.
Client · Regional FMCG Major
600 ppm
Line Speed
7 days
Shutdown
14 days
Ramp to 90%+
99.7%
Defect Detection
The Challenge
Line had to retrofit into an existing brownfield site with a 9-day shutdown window. Multi-OEM integration with legacy SCADA was a critical risk.
Our Solution
Pre-fabricated skid approach, off-site staging in Jebel Ali, integration testing before shipment and a phased changeover with redundancy.
Outcome
Changeover completed in 7 days. Line ran at 94% of design speed by day 14 — fastest brownfield ramp benchmarked by client globally.
Project Gallery
On-site execution




Up Next
